A momentous project.
This is one of the largest transit projects in the U.S. and unlike any in Austin’s history. It’s going to revolutionize how we get around, but it’s not going to happen overnight. Integrating a world-class light rail system into our existing infrastructure will be a long and complex process. Learn more about the major steps of the process and see the latest updates below.
The Steps
1.
Approved & Established
2020 – 2021

Project was approved by Austin voters. ATP was formed to implement the light rail and assembled a team of transit experts.
2.
Defining Scope & Goals
2022 – 2023

Conducted a community-driven process to determine the project goals and formalize the Light Rail Implementation Plan.
3.
Planning, Design & Project Development
2023 – 2026

ATP is currently working on preliminary design and engineering, environmental review, delivery planning, and completing key steps to fulfill federal funding requirements.
4.
Engineering & Permitting
2026 – 2027

Detailed designs and technical specifications will be finalized, and all necessary permits and land will be secured.
5.
Construction & Testing
2027 – 2033

The ground will be prepped and excavated. Light rail tracks, stations, and pedestrian and cyclist paths will be built. Trains will be manufactured, delivered and tested.
6.
Open for Service
2033

Austin’s light rail will officially open with 9.8 miles of track, stretching from 38th to Oltorf and east from Downtown to East Riverside.
Updates
See what’s
coming up.
